Eastwood Urethane primer is a two-component surfacer designed for overall jobs.
It fills well, sands easily and provides excellent color holdout for all top coats. Mixes 4:1 with 50241 ZP catalyst. May be applied over Eastwood Epoxy primers, old paint, body filler & even bare metal. Ideal for block sanding in 3-4 hrs after application. When primer is mixed 4:1 with activator it makes 5 spray-able quarts. Primer is VOC 4.8 lbs per gallon.
This product can not be shipped to California
If you’re sanding primer or body filler you have to check out the that gives you laser straight panels while keeping you and your shop clean because it eliminates 95% of the sanding dust.
Option
To reduce film build, 4:1 mixture may be cut by up to 20% with a urethane-grade reducer. Doing this may also improve the flow and leveling of primer. Eastwood suggests using a Zero-VOC reducer to avoid potential compliance issues. Use caution in mixing materials as epoxy primer may begin to gel after approximately two hours (at 70 °F).
| HVLP Gun | Fluid Tip 1.5-1.7 mm Spray Pressure 8-10 psi at Air Cap (25-30 psi at regulator before gun) |
| Conventional Gravity | Fluid Tip 1.6-2.0 mm Spray Pressure 40-50 psi |
| Conventional Siphon | Fluid Tip: 1.7-2.0 mm Spray Pressure 40-50 psi |
| HVLP Gun | Fluid Tip 1.2-1.4 mm Spray Pressure 8-10 psi at Air Cap (25-30 psi at regulator before gun) |
| Conventional Gravity | Fluid Tip 1.4-1.6 mm Spray Pressure 40-50 psi |
| Conventional Siphon | Fluid Tip: 1.5-1.6 mm Spray Pressure 40-50 psi |
APPLICATION INSTRUCTIONS
Eastwood 2K Urethane Primer Surfacer should be applied in two medium wet coats, with a 10-15 minute flash period between each (at 70 °F). Typically, two coats is enough to achieve the desired 2 mil. dry film thickness, though more material may be applied as needed.
Urethane Primer Surfacer may be topcoated after approximately 30 minutes, or up to 18 hours (at 70 °F with sufficient cross-ventilation), with no additional prep required. After 18 hour recoat window, primer MUST be sanded prior to topcoat application for adhesion purposes.